UNIVERSITY OF WARWICK – LAKESIDE STUDENT ACCOMMODATION REFURBISHMENT
Total Regen worked with University of Warwick to undertake a 10-week, fast-track refurbishment project across its Lakeside House Student Accommodation scheme.
Project details:
Client: J Tomlinson
Team: Total Regen
Type: Refurbishment
Location: Warwick
Project value: £4.8m
Procurement: Competitive Tender
Project Overview
During the summer of 2019, Total Regen was appointed to complete a £4.8m refurbishment scheme across 304 bedrooms and en-suite bathrooms plus accompanying communal areas at Warwick’s Lakeside House student accommodation scheme. Works included rewiring of the building’s electrical system, mechanical containment works, replacement of emergency lighting, carpets, shower rooms, fire alarm and data cabling, as well as refreshments to internal decorations.
The Total Regen Solutions
10-week programme
All works were undertaken during the summer period whilst student accommodation was temporarily vacant. It was critical that the scheme was completed in time for the arrival of students in time for the new academic year, which was made possible by excellent communication between all parties, uncompromising health and safety standards, as well as the project team’s familiarity with all areas of the university’s campus.
Collaborative decision-making
During week 4 of the programme, we discovered that the design intent of the flooring and ceiling was significantly different to actual conditions. Upon discovery, we quickly employed an additional Site Manager and utilised split shifts (working both AM and PM) to accommodate revised ceiling and floor construction details. We also called upon the resources of specialist subcontractors Park Ceiling Ltd to protect the programme and ensure the project was completed on time.
Tried-and-tested supply chain
Having previously undertaken comprehensive refurbishment works across multiple areas of the university, Total Regen was able to call upon the same tried-and-tested subcontractors and merchants as before. This was instrumental in easing co-ordination of activity on site, with up to 130 operatives on site during peak times.
The project was completed both on time and budget and to a high-quality finish, ready for students to inhabit in September.
PROJECT ACHIEVEMENTS
ON TIME AND BUDGET DELIVERY – the project was completed both on time and budget and to a high-quality finish, ready for students to inhabit in September
TRIED-AND-TESTED SUPPLY CHAIN – having previously undertaken comprehensive refurbishment works across multiple areas of the university, Total Regen was able to call upon the same tried-and-tested subcontractors and merchants as before
EXCELLENT CO-ORDINATION – during the project, there were up to 130 operatives on site during peak times. As principal contractor, Total Regen ensured sound co-ordination and efficiency of all parties via regular, transparent communication, comprehensive risk management and health and safety audits, and continuous programme reviews
ENSURING MINIMAL DISRUPTION – whilst student accommodation buildings across campus were vacant throughout the refurbishment scheme, other areas of the university were still live, with graduate events and conferences taking place during the summer. Total Regen ensured minimal disruption to the university’s continued operations and planned activities via careful programming, considerate parking and traffic management, and clear signage of works